Confederation Line - Stage 1
BRT (Bus Rapid Transit)
Integrated bus loops at hub and terminus stations will allow riders on Bus Rapid Transit to quickly make connections.
Downtown Tunnel
A 2.5-km downtown tunnel will ease congestion in the core.
Walking and Cycling
Stations integrated with pedestrian and cycling pathways will promote healthy, sustainable commuting.
Schedule of Project Background
November 2008 | Council Approves Transportation Master Plan |
May 2009 | Council Approves Alignment Report |
August 2010 | Province Approves Environmental Assessment |
November 2010 | Preliminary Engineering Commences |
December 2011 | Request for Proposals to Design & Build |
December 2012 | Proposal Selection |
February 2013 | Contract Awarded |
February 2013 | Construction Commences |
2019 | Full Revenue Service |
Station features
Tunney’s Pasture | Bayview | Pimisi |
Lyon | Parliament | Rideau |
UOttawa | Lees | Hurdman |
Tremblay | St-Laurent | Cyrville |
Blair | Downtown Tunnel | Belfast Yard |